Our new hall in Lage
Our own new steel hall: full electrical installation, main distribution and a PV system on the roof. We have worked here since July 2025.
Task and solution
The task
We needed more room for offices, production and stores. From September 2024 our own steel hall with offices and a mezzanine went up in Lage.
Our work
We did the whole electrical installation, the main cabinets and the PV system on the roof ourselves.
Result
We moved in in July 2025 — offices, production and stores are now under one roof.











More of our work

100 kWp commercial rooftop system
East-west flat-roof system on a retail store — with inverters on the roof and an AC cabinet.

PV system and wallbox for a family home
Panels on the pitched roof and the flat garage roof, inverter in the garage and a wallbox for the car.

Electrical installation and PV for a new company building
From conduits in the concrete to the finished offices: main distribution, sub-distributions, network and a PV system on the flat roof.